Utah construction lien and bond deadlines: 20-day preliminary notice, 90 or 180 days to file

Utah lien claimants file a preliminary notice in the State Construction Registry within 20 days of starting work, record the lien within 90 or 180 days, and sue within 180 days.

By the Construction Utah News desk · Reviewed Oct 31, 2026 · 1 min read

Utah's construction lien law is Title 38, Chapter 1a. Public payment bonds are covered by § 63G-6a-1103. This is a summary, not legal advice.

Preliminary notice

A person who wants to claim a construction lien must file a preliminary notice with the State Construction Registry no later than 20 days after starting construction work on the property (§ 38-1a-501).

Recording the lien

The notice of construction lien is recorded with the county recorder no later than 180 days after final completion of the original contract if no notice of completion is filed, or 90 days after a notice of completion is filed, but never more than 180 days after final completion (§ 38-1a-502).

Enforcing

An action to enforce the lien must be filed within 180 days after the notice of construction lien is filed, with a notice of pendency of action (§ 38-1a-701).

Public jobs

  • Performance and payment bonds of 100% of the contract price (§ 63G-6a-1103).
  • A claimant not paid in full within 90 days after its last work may sue on the payment bond.
  • The action must be filed within one year after that last work.
  • Retention is capped at 5% (§ 13-8-5).

Summary for general information, reviewed 2026-10-31. Not legal advice; check the source before relying on a deadline or threshold.