Bids & Lettings · Iron County

I-15 South Cedar Interchange goes to bid Nov. 24 with a $60 million to $80 million estimate

UDOT will convert Cedar City's south I-15 interchange to a single-point urban interchange and widen the interstate. Prequalification is mandatory, and construction is expected from spring 2027 to spring 2029.

By the Construction Utah News desk · Oct 31, 2026

The largest project now advertised by the Utah Department of Transportation is the I-15 South Cedar Interchange and widening in Cedar City. UDOT posted it in Contractor Zone on Oct. 31, 2026, with a bid opening on Tuesday, Nov. 24. The listing gives an engineer's estimate of greater than $60 million and up to $80 million, the highest band among the 11 projects UDOT is advertising.

The project is PIN 21678, federal-aid project F-I15-2(94)56, in UDOT Region 4. Its work category is "Upgrade Existing Interchange."

What UDOT is building

UDOT's project page says the existing interchange will become a single-point urban interchange (SPUI), which brings all left turns on the interstate to a single traffic signal. UDOT lists these goals:

  • enhance the safety and operation of surrounding intersections
  • reduce off-ramp queues that extend onto mainline I-15
  • improve pedestrian and cyclist safety and connectivity through the interchange
  • improve overall connectivity and experience for users

The project adds sidewalks and a pedestrian bridge south of the interchange. The Providence Center Drive/Royal Hunte Drive and Main Street/Cedar Boulevard intersections will be widened to include dual left-turn lanes in all directions. The Contractor Zone title also includes widening.

Schedule

UDOT's project page lists these milestones: an environmental assessment on Dec. 1, 2024, 30% design on Sept. 1, 2025, and 60% design on March 1, 2026. It now says design is complete, a contractor is anticipated to be selected in fall 2026, and construction is anticipated from spring 2027 to spring 2029, subject to weather and material availability.

How it compares

South Cedar is in a different class from the rest of UDOT's November work. Even at the top of every estimate band, the other 10 advertised projects add up to about $45.5 million, less than the bottom of South Cedar's $60 million band. The next-largest is the I-15 rehabilitation from 7200 South to 5300 South in Salt Lake County, estimated at $10 million to $15 million.

UDOT's project page also has sections on the project's environmental assessment and noise barriers, and a public information hotline for questions from residents and businesses.

Bidding terms

  • Prequalification: mandatory. Only UDOT-prequalified contractors may bid.
  • Price plus time: the listing says it is a P+T project, so bidders submit both a price and a time.
  • Payroll: the electronic certified payroll program is required.
  • DBE goal: 0.00%.
  • Retention: UDOT says it will not hold retention, citing Utah Code § 13-8-5.
  • Submission: through Masterworks Contractor Bidding, from Contractor Zone.

What it means for subcontractors

A SPUI with a pedestrian bridge, widened intersections and interstate widening will need structures, earthwork, paving, signals, lighting, drainage, traffic control and concrete flatwork. Because UDOT holds no retention on the prime contract, Utah Code § 13-8-5 requires that the prime hold no higher percentage from its subcontractors. Section 13-8-5 caps retention at 5% and says the percentage between a prime and its subcontractors must match the owner's when the owner holds less than 5%.

Utah's Procurement Code also requires performance and payment bonds of 100% of the contract price on construction contracts (Utah Code § 63G-6a-1103). A subcontractor or supplier not paid in full within 90 days after its last work may sue on the payment bond, and must do so within one year.

Iron County's other job

Iron County also has the SR-56 bridge deck preservation over the Union Pacific tracks, PIN 20778, which opened bids on Nov. 5 with an estimate of up to $500,000. It is state-funded and does not require prequalification.

Iron County is in UDOT Region 4, based in Richfield. Our Iron County hub lists the county's 11 DFCM-prequalified firms, and the project is on our bids page.