No retention on UDOT jobs: what Utah's 5% cap, 20-day preliminary notice and bond rules mean for subcontractors
UDOT says it will not hold retention on any of its 11 advertised projects, and Utah law then bars primes from holding more from subcontractors. Here is how Utah's retention, lien and bond rules fit together.
Every project the Utah Department of Transportation is advertising in Contractor Zone carries the same note, in capital letters: "The department will not hold retention on this project. Per Utah State Code § 13-8-5 (1) prime contractors cannot hold retention." This explainer summarizes the statutes behind that note and the other payment rules subcontractors work under in Utah. It is not legal advice.
Retention: the 5% cap and the pass-through rule
Utah Code § 13-8-5 limits retention on construction contracts, including highway work. Retention withheld from any payment may not exceed 5%, whether it is held by the owner or public agency from the original contractor, by the original contractor from a subcontractor, or by a subcontractor. The total withheld may not exceed 5% of the total construction price.
The section also ties the subcontract rate to the owner's. If the retention percentage in the owner's contract with the original contractor is less than 5%, or is reduced below 5% before completion, the same lower percentage applies between the original contractor and its subcontractors, and between subcontractors. When UDOT holds nothing, the prime may hold nothing.
Where retention is held, the statute requires it to be deposited in an interest-bearing escrow account. Retention and accrued interest must be released on the contractor's billing statement within 45 days of the dates the statute sets out, and the contractor must distribute interest on retainage to subcontractors on a pro rata basis.
UDOT's contractor resources page links a memo titled "UDOT Central Construction 2022-1 Removal of Retention."
Private work: preliminary notice and liens
Utah's construction lien law (Title 38, Chapter 1a) runs on a state registry:
- Preliminary notice: a person who wants to claim a construction lien must file a preliminary notice with the State Construction Registry no later than 20 days after starting construction work on the property (§ 38-1a-501).
- Recording the lien: the notice of construction lien goes to the county recorder no later than 180 days after final completion of the original contract if no notice of completion is filed, or 90 days after a notice of completion is filed, but no later than 180 days after final completion (§ 38-1a-502).
- Enforcing: an action to enforce the lien must be filed within 180 days after the notice of construction lien is filed (§ 38-1a-701).
Public work: bonds
Liens do not attach to public property. Under the Utah Procurement Code, a contractor awarded a construction contract must deliver a performance bond and a payment bond, each equal to 100% of the contract price and executed by a surety company authorized to do business in Utah, or in another form satisfactory to the procurement unit (§ 63G-6a-1103). A person who furnished labor, service, equipment or material and has not been paid in full within 90 days after its last day of work may sue on the payment bond. The suit must be brought in a county where the contract was performed and within one year after that last day.
What to do on a UDOT job
- Check that your subcontract does not withhold retention; on current UDOT projects, § 13-8-5 does not allow it.
- Get a copy of the prime's payment bond before you start.
- Track your last day of work or delivery; the 90-day and one-year bond clocks run from it.
- Ask how the prime's schedule affects yours. All 11 current UDOT listings are price-plus-time (P+T) projects, where bidders compete on contract time as well as price.
What to do on a private job
- File preliminary notice in the State Construction Registry within 20 days of starting, every time.
- Watch for a notice of completion, which shortens your lien deadline to 90 days.
- Calendar 180 days from recording to file suit.
See our lien and bond guide and the current UDOT projects on our bids page.
Utah Code § 13-8-5
Utah Code § 38-1a-501
Utah Code § 38-1a-502
Utah Code § 38-1a-701
Utah Code § 63G-6a-1103
UDOT Contractor Zone: advertised projects (read Oct. 31, 2026)
UDOT: Construction contractor resources
Spot an error? Email corrections to the editor. Facts in every story come from the sources listed above.